Wednesday, March 4, 2009

More Pool Progress

The Bathhouse with the forms removed from it Wednesday. They are now setting up the forms for the inside walls of the bathhouse which should be poured on Thursday. Beautiful weather!


They also poured another section of the pool floor. The gutter people have not arrived yet and so the final section of the pool will not be poured until the gutter is put in - THE POOL WILL BE DEEPER THAN IT LOOKS NOW!!!!!!! THE GUTTER WILL ADD ANOTHER 12 - 14 INCES OF DEPTH TO THE ENTIRE POOL!!!!!!!