They began the process of building the rebar mesh that will be inside the walls when they pour them early next week. The upright rebar had been in place since the footings were poured and now they are adding the horizontal rebar and wire tying it all together.
The pool sump area is now enclosed with a metal rail.
Roth and Troyer have one wall done with the horizontal rebar in this photo and continue work on the east side
No comments:
Post a Comment