Friday, April 17, 2009

Pool Project Progresses Some More

This is the door to the outdoor bathroom - they poured the pad this week that is adjacent to the door. This is in the south west corner of the building.
The pad behind the pump area was also poured this week.
The forms are set up and ready for concrete to be poured around the entire pool. This will make it easier to see how deep the pool is - the gutters which are the pool drainage system raised the depth of the pool over 12 inches.
The roof is nearly completed and plumbing work has been constant throughout the week.