Pages
(Move to ...)
Home
Exeter Village Ordinances - Chapter 1 Civil Admini...
Exeter Village Ordinances: Municipal Planning
Exeter Village Ordinances: Fire Regulations
Exeter Village Ordinances: Public Utilities
Exeter Village Ordninances: Public Ways and Proper...
Exeter Village Ordinances: Business Regulations
Exeter Village Ordinances: Vehicles and Traffic
Exeter Village Ordinances: Misdemeanors
Exeter Village Ordinances - Commissions and Boards...
Stories from Exeter
Photos from Exeter
Exeter's Strategic Plan
Exeter Community Guide
Exeter Aquatic Center Rules
Exeter Service Record Book World War I and II
▼
Saturday, March 14, 2009
Special Events in Exeter Coming Soon!!!
›
The next few weeks offer plenty of special opportunities to eat in Exeter - and help some great causes at the same time. Don't miss the...
Wednesday, March 11, 2009
Bathhouse Progress
›
Work continues on the pump pit. The bathhouse front entrance - the large opening is for a roll up door for the main entrance with a small do...
Thursday, March 5, 2009
Bathhouse interior walls poured on Thursday
›
Thursday afternoon they poured the interior bathhouse walls These are the interior walls formed up Thursday morning The sand is being packed...
Wednesday, March 4, 2009
More Pool Progress
›
The Bathhouse with the forms removed from it Wednesday. They are now setting up the forms for the inside walls of the bathhouse which shoul...
Tuesday, March 3, 2009
Bathhouse walls poured on Tuesday
›
Roth and Troyer got the bathhouse walls formed up on Monday and finished Tuesday. The cement pumper truck came around 1:00 p.m. and the cem...
Monday, March 2, 2009
GOING TO STATE!!!!!
›
Exeter-Milligan is heading to the State Tournament after a win over Diller-Odell 53-38 in the District Final. The Twolves jumped out to a...
Friday, February 27, 2009
Bathhouse Construction Progress
›
On Thursday afternoon, Roth and Troyer Construction arrived with several truckloads of forms and workers. They began the process of building...
Wednesday, February 25, 2009
Zero Entry Area will be close to Parking
›
In a web post of February 5th it stated that "If you drive by or look at the picture you can see that this area is very close to the ex...
Pool Floor nearly completed
›
As you can see from this picture, much of the pool floor is poured. The section on the left side of the picture will be poured Thursday and...
Friday, February 20, 2009
Exeter-Milligan Lady Timberwolves Successful Again
›
The first game of the Sub-Districts the Lady T-wolves played Bruning/Davenport. The girls came out winning 53-38. Scoring: Amber Filipi:...
‹
›